PermitFlow
HSE Manager
Back to permits
PTW-2026-1043Approved

Valve chamber internal inspection

Confined Space · Station B – Chamber V-12

Work Details

Requester
Ahmed Al-Rashid
Contractor
Gulf Pipeline Services
Risk level
Critical
Validity
2026-08-29 → 2026-08-29

Internal visual inspection of valve chamber V-12. Atmosphere tested and ventilated.

Safety Precautions

  • Atmosphere test < 30 min before entry
  • Standby attendant at entry point
  • Rescue plan in place
  • Continuous ventilation

History

  1. Permit created
    Ahmed Al-Rashid · 2026-08-27
  2. Approved
    HSE Manager · 2026-08-28